Understanding of XLPE Cable System Commissioning using Partial Discharge Measurements during AC HV Tests

##plugins.themes.academic_pro.article.main##

Vasudev Patil
Arun Yargole
Fazle Masood
Imteyaz Siddiqui
Simon Sutton

Abstract

This paper is based on the work done by Altanova Group, India, and describes the process and procedures used in a Partial Discharge (PD) investigation on a cable circuit during the AC withstand test. The paper focuses on the two most common approaches employed, namely, soak tests and resonant tests. In the latter case, the paper describes two approaches to performing the measurements and the relative benefits of each. De-noising the acquired data using T-F map analysis is also described, and real-world examples are given in the two case studies. These detail EHV resonant tests, one performed where all the accessories were monitored simultaneously and another where each accessory was tested in turn before relocating the PD monitoring equipment to the next location. In both cases, the application of T-F maps shows how different PD sources, such as external corona, can be identified and hence segregated.

##plugins.themes.academic_pro.article.details##

How to Cite
Patil, V. ., Yargole, A. ., Masood, F. ., Siddiqui, I., & Sutton, S. . (2022). Understanding of XLPE Cable System Commissioning using Partial Discharge Measurements during AC HV Tests. Power Research - A Journal of CPRI, 18(1), 85–91. https://doi.org/10.33686/pr.v18i1.1101

References

  1. IEC 60270. High-voltage test techniques- Partial discharge measurements; 2000.
  2. Gouda O, El Faraskoury A. Experiences with on-site AC test combined with partial discharge measurements. CIRED, paper 0029; 2013.
  3. Herrman U, Kluge A, Plath R. After-installation testing of HV/EHV extruded cable system – procedures and experiences. Jicable’07; 2007.
  4. Sutton S, Plath R, Schroeder G. The St. John Wood – Elstree experience – Testing a 20km long 400kV XLPE-insulated cable system after installation”, Jicable’07; 2007.
  5. Caprara A, Paschini L, Ciotti G. Partial discharge measurements during AC voltage test: a fast and effective method for the site commissioning of long EHV XLPE cable systems”, Jicable”19, Paris; 2007.